This plant operates and manages a 950,000 gallons per day (gpd) wastewater treatment plant under contract with the City of Buda. GBRA assumed operations of the Buda WWTP in October 2001 after the plant expansion in July 2001. Another plant expansion was completed in 2007. Located in the environmentally sensitive Onion Creek watershed, the plant is operated as a "complete mix, activated sludge system" utilizing two clarifiers for biosolids and phosphorus removal. Sludge handling is facilitated by a belt filter press.
Process monitoring is performed on-site, with more advanced monitoring and testing procedures completed by the
GBRA Regional Laboratory.
- Location: Buda, Texas
- Start-up date: 1985
- Expanded to current capacity: 2007
- GBRA assumed operations: October, 2001
- Capacity: 950,000 gpd
- Service area: City of Buda
- Service population: 4,000
Contact
Darel Ball, Division Manager
Phone/Fax: 512-312-0526
E-mail: